Lithium Plus Minerals (LPM) is planning a small underground lithium mine at the Lei Deposit, part of its Bynoe Lithium Project, located on the Cox Peninsula south-west of Darwin near other operating lithium mines.
If approved, lithium ore from the mine would be crushed and screened on site, then trucked to Darwin Port via existing roads for export with no chemical processing of lithium proposed on-site.
Lithium is used in rechargeable batteries for electric vehicles, renewable energy storage, mobile phones and other technologies that support cleaner energy.
LPM has advanced the Lei Lithium Deposit through the NT environmental approval process, completing baseline studies for groundwater and surface water, flora and fauna surveys, stakeholder engagement, and geochemical assessments, which culminated in submission of a Referral Application to the NT EPA in 2024.
The NT Government has requested additional information via a Supplementary Environmental Report (SER), which will further address the project’s potential impacts and how they would be managed.
A 20-year Mining Lease has been granted for the proposed mine, however, environmental and other approvals, including an Authority Certificate from the Aboriginal Areas Protection Authority, are needed before mining can start.

Small Underground Mine
20-Year Mining Lease
80-110 Mining Jobs
No Chemical Processing

The Lei Lithium Project is expected to use less water than some other mining projects because it does not plan to process lithium on-site.
Water will mainly be used for:
The mine is expected to meet its own operational water needs, except during extreme drought. Drinking water and water for office use would be delivered to the site by tanker.
Any release of water from the site would only happen under an approved licence and only when water quality requirements are met.
A Water Management Plan will be implemented to guide the separation and management of clean stormwater, mine-affected water, and operational water to protect downstream environments, surface water flows, and groundwater values.
The Lei Lithium Project will create approximately 120–150 construction jobs and around 80–110 operational mining jobs with most work at the mine carried out by specialist construction and mining contractors.
LPM will seek to provide early visibility of upcoming work packages where practicable and encourage contractors to identify opportunities for local businesses, suppliers and workers.
The workforce is expected to live locally or in the surrounding area with no on-site accommodation camp proposed. Bus transport is expected to be provided for workers travelling to and from Palmerston, with pick-up points along the route.
LPM has engaged a cultural heritage specialist to conduct a survey with representatives of the Larrakia people and to consult with them on the findings.
LPM will apply to the Aboriginal Areas Protection Authority for an Authority Certificate before any project works begin. This process helps identify and protect sacred sites.
LPM is committed to working with Aboriginal employment, training and business organisations to identify practical engagement and participation opportunities for Aboriginal people and businesses.
The Lei Lithium Mine will be underground, significantly reducing surface disturbance compared with an open-cut mine.
LPM proposes to manage dust, noise and visual impacts by keeping a vegetation buffer along Fog Bay Road, spraying water on dusty roads and work areas, covering truck loads, monitoring dust from site activities and responding to community enquiries and complaints.

Lithium ore will be trucked from the mine to East Arm Wharf at Darwin Port using an existing network of established roads already used by road trains. The haulage route will be Fog Bay Road, Cox Peninsula Road, Stuart Highway, Tiger Brennan Drive, and Berrimah Road to East Arm Wharf.
During peak operations, the project is expected to generate about 68 two-way vehicle movements per day, including about 20 heavy vehicle movements. Heavy vehicles will only operate during daylight hours with movements expected to be spread across an operating period between 6:00am and 6:00pm.
A traffic study has been completed. While some sections of the road access to the mine need maintenance, the traffic study found that the existing road network can comfortably handle the extra traffic from the Lei Lithium Project.
To help manage and improve road safety, LPM will:
LPM will prepare a Mine Closure Plan (MCP) for the Lei Lithium Mine that will explain how disturbed areas will be made safe, stable, and non-polluting after mining is finished.
Closure planning will include removing temporary infrastructure, managing mine openings and waste materials, rehabilitating disturbed land and monitoring water quality, vegetation and land stability.
A concept MCP will be submitted as part of the SER. Rehabilitation planning will continue as the project develops.
The MRE for the Lei Deposit, as announced on 15 July 2026, is summarised in the table below (at a 0.5% Li2O cutoff):

No Measured category has been classified at this time.